CategoryMaterials & Grade Selection
Titanium weight
calculator.
Estimate what a plate, length of bar or hollow tube should weigh before comparing prices per kilogram. The calculator shows the density, unit conversions and metal volume behind the answer.

Quick answer
Choose the geometry the supplier will actually deliver. Enter finished stock dimensions, choose a density and specify quantity. A tube needs its outside diameter and one wall thickness. Compare the resulting theoretical mass with the quotation’s billing basis, cutting allowance and separately indicated packaging.
Calculate your stock mass
01 / Which mass belongs on the enquiry?
Which mass belongs on the enquiry?
When a buyer asks what a titanium plate weighs, the first question is which plate the supplier is pricing. Imagine a drawing for a finished carrier plate with pockets, through-holes and machined faces. Three suppliers could offer the same alloy but supply a mill rectangle, a sawn blank with room for finishing, or the completed carrier. A mass derived from the finished CAD model describes only the third item. It cannot tell you how many kilograms of raw plate the machining workshop must buy. Mark the outline of the purchased item on the drawing before comparing the three prices.
The calculator above treats each piece as a solid plate, solid round bar or straight round tube with uniform dimensions. It calculates the amount of metal in that ideal shape. The order quantity multiplies the per-piece result. Packaging, crop ends, machining waste, retained cutoffs, attached fittings and manufacturing variation require their own entries when applicable. Make a note of whether the drawing dimensions refer to starting stock, a cut blank or the final part. You can then return to the estimate after a drawing revision and tell exactly what changed.
A practical example is a fixture plate with a finished width of 480 mm. The approved machining plan may call for a blank 500 mm wide. If the supplier delivers that wider blank, use 500 mm on the buying line. If the supplier also machines and delivers the final item, ask whether the price includes the removed material and what mass will appear on the packing list. A fixed price per finished piece can include stock consumption even though the shipment only contains the machined plate. The two numbers answer different questions and can both be correct.
For a long product it is often easier to start with mass per metre. Enter a length of 1,000 mm and a quantity of one. Multiply the result by the ordered length in metres, or rerun the calculator with the full cut length and quantity. Record the method. A value labelled simply “1.42 kg” is ambiguous if one line describes one metre of bar and the next describes a piece three metres long. A column heading of kg/m or kg per cut piece removes that ambiguity before someone transfers the result into an order.
Keep the estimate attached to the correct revision and quote line. Useful fields include the product form, mill grade, dimension units, density and its source, piece count, calculated mass and billing basis. A purchasing colleague should be able to reproduce the result without guessing whether the entered thickness included machining stock. For an order with mixed lengths or more than one shape, calculate each line separately. Add the line masses only after each item has been converted to the same unit, and keep the breakdown available for receiving.
02 / Match the cross-section to the ordered shape
Match the cross-section to the ordered shape
For a rectangular plate, multiply length by width by thickness to obtain volume. With dimensions in millimetres, this gives cubic millimetres. Divide by 1,000 to obtain cubic centimetres before multiplying by a density in grams per cubic centimetre. Divide the resulting grams by 1,000 to obtain kilograms. Equivalently, multiply all three millimetre dimensions by the stated density and divide by one million. That last divisor applies to this combination of units only. Write at least one complete calculation with units when a spreadsheet is being checked or built for the first time.
Take the Grade 2 plate in the table. A length of 1,000 mm, width of 500 mm and thickness of 6 mm give 3,000,000 mm³. That is 3,000 cm³. At 4.51 g/cm³ the result is 13,530 g, or 13.530 kg. Ten pieces have a theoretical metal mass of 135.300 kg if all have those exact nominal dimensions. Entering the same dimensions under Grade 5 with the specified 4.42 g/cm³ density gives 13.260 kg per plate. The volume stays fixed when only the material selection changes. The result is a useful cross-check on a calculator or quotation.
For round bar the cross-sectional area is π times the diameter squared divided by four. Multiply by the length. A bar of diameter 20 mm has an area of approximately 314.159 mm². At a length of one metre its volume is approximately 314.159 cm³. A common spreadsheet error is to treat the diameter as the radius in the expression πr². That produces four times the intended area. A drawing may also show a radius for a rounded corner, which must not be copied into the input for the stock diameter.
For a tube, subtract the inner circle from the outer circle. If outside diameter is D and wall thickness is t, the inside diameter for an ideal concentric tube is D minus twice t. The metal cross-section can be written as πt(D − t). Both formulas describe the same geometry. For an outside diameter of 25 mm and a 2 mm wall, the bore is 21 mm. A wall value of 4 mm would describe a different tube. The input is the thickness of one wall, even if two walls appear in the section shown on a drawing.
For a stepped shaft, divide the profile into nonoverlapping cylinders and add their masses. Deduct a through-hole once, over its actual length. For an irregular machined face, an approved CAD volume may be more reliable than a sum of rectangles. Be clear about the boundaries of every volume you add or subtract. A counterbore inside a previously deducted through-hole removes only the surrounding annular material over the counterbore depth. Subtracting the full counterbore cylinder after deducting the complete through-hole would count part of the missing metal twice.
| Illustrative order, dimensions in mm | Metal volume per piece | Theoretical mass with stated density |
|---|---|---|
| Grade 2 plate, 1,000 × 500 × 6 | 3,000 cm³ | 13.530 kg at 4.51 g/cm³ |
| Grade 5 plate, same dimensions | 3,000 cm³ | 13.260 kg at 4.42 g/cm³ |
| Grade 2 round bar, Ø20 × 1,000 | 314.159 cm³ | 1.417 kg, rounded |
| Grade 2 tube, OD 25, wall 2, length 1,000 | 144.513 cm³ | 0.652 kg, rounded |
| Ten Grade 2 plate blanks as above | 30,000 cm³ in total | 135.300 kg before packaging |

A rectangle uses its full cross-section. For the tube, subtract the bore from the outside cylinder.
03 / Choose the density and control the units
Choose the density and control the units
The calculator provides two published nominal densities so the buyer can reproduce its figures. The TIMETAL 50A sheet gives 4.51 g/cm³ for commercially pure Grade 2. The TIMETAL 6-4 data sheet used here gives 4.42 g/cm³ for the Grade 5 alloy. The sources are linked below. These are typical material data for estimating mass. They do not identify an unknown alloy, impose an acceptance tolerance on a delivered plate or replace a material certificate. Where the contract calls up another documented density, select the custom option and record that source with the estimate.
A rounded number can be appropriate for transport planning and insufficient for a close commercial reconciliation. For example, changing an assumed density from 4.51 to 4.50 g/cm³ reduces the estimate for the 3,000 cm³ plate by 30 g. Across one hundred identical plates that difference accumulates to 3 kg. Neither calculation establishes what the scale must read. The example demonstrates why both parties should identify the density used before investigating a difference in invoice mass. It also shows why adding more decimals to the result cannot recover precision missing from the density input.
Dimension units require a separate check. An international inch is exactly 25.4 mm. A plate described as 1 inch thick and 12 inches wide has dimensions of 25.4 mm and 304.8 mm in those directions. The calculator converts every active length dimension when the unit selector changes. Type the dimensions consistently in the selected system. If the drawing mixes a metric length with an inch wall callout, convert one input before entering it. Changing the label on a spreadsheet cell without changing the number silently changes the geometry.
Cubic units magnify a conversion mistake. A cubic inch corresponds to 25.4 multiplied by itself three times in cubic millimetres. A surface area uses only two factors, and a length uses one. Where a CAD model gives cubic centimetres directly, it is possible to multiply by a density expressed in grams per cubic centimetre and obtain grams immediately. Do not convert a CAD volume as if it were one linear dimension. State the unit beside the volume when transferring a value from a model report into the purchasing spreadsheet.
Mass and force have different meanings. The numeric outputs here are kilograms and pounds of mass. They are suitable for a stock estimate and for comparison with masses on shipping records. They do not establish the load capacity of a rack, the rating of a lifting accessory or how an oversized crate can be handled. If a carrier or receiving site requests lifting information, provide the actual packed dimensions, gross mass, centre of gravity and the approved handling details for the shipping unit. That information belongs with the packing plan and may differ between shipments of the same stock.

For the same 3,000 cm³ plate, the selected TIMET densities give 13.53 kg and 13.26 kg respectively.
04 / Find the range allowed by the drawing
Find the range allowed by the drawing
Dimensions on a stock drawing are often allowed to vary. A buyer can estimate an interval before comparing the theoretical figure with a weighbridge or scale reading. For a simple plate with fixed positive length and width, mass varies directly with thickness. Suppose the purchase drawing in a worked example permits a thickness of 5.90 to 6.10 mm and fixes the plan dimensions at 1,000 by 500 mm for this calculation. At 4.51 g/cm³, the resulting limits are 13.3045 and 13.7555 kg. This interval is calculated from an illustrative drawing. It is not a mill tolerance or a weight guarantee.
The same approach applies when length and width also have limits. For rectangular stock with independent positive dimensions, multiply the three lower limits for a lower bound and the three upper limits for an upper bound, using the assumed density in both cases. If the drawing constrains two dimensions together, those extreme combinations may never occur in an acceptable part. A worst-case arithmetic bound describes what the stated assumptions allow. It does not predict how production will be distributed within that interval or how likely one lot is to reach its extremes.
Round bar behaves differently because diameter is squared. Compare 20 and 20.2 mm as two illustrative diameters at the same length and density. The mass ratio is (20.2/20)², or 1.0201. A diameter increase of one percent increases the calculated mass by 2.01 percent in this example. A small increase in diameter matters more than the same percentage increase in length. This is helpful when investigating a bar delivered with grinding allowance. Check the ordered condition and measure the received diameter before attributing excess mass to the grade.
For a tube, outside diameter and wall interact. At a fixed outside diameter the bore shrinks when the wall grows. The cross-section formula already accounts for that change. If the controlling requirements are outside and inside diameters, use those measurements together or convert them to a consistent wall input. Do not independently tighten three dependent dimensions in the estimate. With uneven wall or ovality, a single reading and an assumption of perfect concentricity have limits. Follow the agreed dimensional inspection plan if the acceptance decision concerns wall thickness rather than total mass.
Look closely at the meaning of an average. Ten nominal plates that weigh close to the expected total can still contain individual pieces outside a dimensional tolerance. Conversely, a crate with more metal than the nominal estimate can contain fully conforming plates if they sit toward the high side of an allowed thickness interval. Separate the commercial reconciliation from the dimensional acceptance. Check quantities and scale tare first, then identify which drawing feature matters, what instrument can measure it and where measurements should be taken on the piece.

A cut plan accounts for each separation and any unusable end. The example does not set a required kerf.
05 / Separate finished pieces from purchased stock
Separate finished pieces from purchased stock
A cut list translates the desired finished pieces into a demand for starting stock. Suppose four finished bars must each measure 240 mm and the approved process allows 2 mm at each end for finishing. Each cut blank is then 244 mm long, so the four blanks consume 976 mm of useful stock length. If the cut plan makes four independent separations and allows 3 mm for each saw kerf, another 12 mm is consumed. The total under those assumptions is 988 mm before end cropping. The example is a layout exercise. Kerf widths, saw setups and actual end allowances must come from the responsible shop.
Keep the remainder visible. A nominal metre of stock would leave 12 mm in the worked layout before any end trim, clamping restriction or length tolerance. If the line requires a clean-up cut or an uncut grip length, four blanks may no longer fit. A quotation based on full stock bars can therefore change abruptly at the boundary between four and three acceptable blanks. Multiplying the net piece mass by the finished quantity alone misses that change. Ask which party owns an offcut and whether a usable remainder can be applied to a later order.
For plate, nesting is a two-dimensional problem. The dimensions of one blank and its mass do not tell you whether multiple blanks can be cut from the purchased sheet. Sketch the orientation, spacing between parts, edge trim and any direction restriction. A long rectangular part may fit across the sheet only when rotated. If grain or rolling direction has been specified relative to a bend or a machined feature, that rotation may be unavailable. Obtain the approved nesting arrangement before agreeing a yield percentage or asserting that another supplier is using too much plate.
Keep three items separate when reviewing cut stock. The theoretical mass of material in the delivered blanks describes the shipment. The parent stock consumed can include kerfs and scrap. The commercial basis may be a fixed price per blank, a price per net kilogram or a charge for the full parent sheet. Ask the supplier to identify the basis in writing. A quotation with a lower rate per kilogram can cost more per delivered part if it applies that rate to a larger amount of purchased stock or excludes cutting charges included by another bidder.
Inspect the units in the cost conversion. For ten equal pieces, divide the agreed total line amount by ten to compare prices per delivered piece. To calculate a rate per delivered kilogram, divide by the total net mass of those same ten pieces. If identical amounts are divided by net finished mass in one bid and gross stock mass in another, the resulting rates answer different questions. Include measuring, cutting, inspection and packing charges consistently in the comparison, and preserve the supplier’s original price basis so it can be checked later.
Read the related technical guide for the companion product or property.
06 / Reconcile the quotation, packing list and scale
Reconcile the quotation, packing list and scale
Receiving can reconcile quantity, drawing dimensions and mass in an orderly sequence. Start with the packing list and count the pieces or bundles against each line. Read the units carefully and determine whether the figure refers to net metal mass or to the gross shipping unit. Look for pallets, timber, blocking, corner protectors and reusable fixtures. A scale reading for the loaded crate cannot be compared directly with the nominal mass of the bare stock unless the other contents and their tare have been accounted for.
Next verify that the estimate describes the condition in which the goods were shipped. A plate supplied with machining stock should be compared with the blank dimensions. A tube with protective caps still fitted includes cap mass on the scale. If the consignment contains several grades or lengths, keep their line weights distinct. The nearest theoretical total might appear to match even when two bundles have been interchanged. Use piece identification and the lot documentation to link a measurement to the correct order line and to the corresponding drawing.
A useful receiving note records gross scale reading, verified tare, resulting net measurement, quantity, calculated nominal mass and the basis of that calculation. State whether the scale is appropriate for the size of the discrepancy under review. A small difference attributed to one short component may lie below what can be resolved by weighing an entire crate. Weighing an agreed sample or a separate bundle on suitable equipment may provide better evidence. Keep the original reading and date rather than replacing it with a corrected theoretical value during reconciliation.
When the discrepancy is material, test simple alternatives before requesting a replacement. A plate recorded as 5 mm instead of 6 mm changes the nominal metal mass by one sixth of the 6 mm value. A bar entered with a radius in the diameter field gives a result one quarter of the intended mass. A tube mistakenly entered as a solid bar includes the missing bore. These errors have recognizable directions and magnitudes. A quick recalculation can show whether one explains the order of difference before anyone opens a quality case.
For the quotation itself, send a short reproducible summary. An example would identify ten Grade 2 plates, the blank dimensions, density reference and the estimated net mass of 135.300 kg. It would also identify the drawing revision, relevant tolerances, permitted cut condition, destination and the requested separation of packing or freight charges. Ask the supplier to confirm its actual delivery condition and commercial weight basis. That gives purchasing a number for comparison, receiving a traceable expectation and the supplier a clear way to explain any legitimate difference.
07 / Build your RFQ
Request a technical quotation
Estimate what a plate, length of bar or hollow tube should weigh before comparing prices per kilogram. The calculator shows the density, unit conversions and metal volume behind the answer.
Information to include
- Shape and stock dimensions
- Units and material grade
- Quantity and cut list
- Tolerance band and billing basis
- Net and gross shipping masses
Build your RFQ checklist
Choose the product and add the information you have. Copy the resulting brief or send your requirements to TiHubs. Submitting an enquiry does not place an order.
08 / FAQs
Questions buyers ask
Why does another calculator give a different result?
Compare the density, unit system, shape and order quantity first. Then check whether it uses wall thickness or inside diameter and how many digits are carried before rounding. A calculator can be internally correct and still describe a different blank.
Can the result determine freight charges?
Use it for the metal portion of an estimate. A packing list should identify any crate, end caps, pallet and other goods. The carrier may apply a separate dimensional or chargeable weight according to its service and the package dimensions.
Is tube nominal pipe size an outside diameter?
Obtain the actual outside diameter and wall from the applicable pipe table or drawing. Enter both in one unit system. Two lines with the same nominal diameter can use different walls and have different masses per metre.
09 / Key takeaways
Keep the purchase requirements connected.
- Shape and stock dimensions
- Units and material grade
- Quantity and cut list
- Tolerance band and billing basis
- Net and gross shipping masses
Technical references
Sources and data scope
References reviewed November 20, 2026. Public source summaries support the discussion; the controlled specification, agreed edition and approved project requirements govern acceptance.
- TIMET — TIMETAL 50A — Typical Grade 2 density used by the calculator.
- TIMET — TIMETAL 6-4 — Typical density of 4.42 g/cm³ on this specific data sheet.
- NIST — SI Units, Length — Source for the inch-to-millimetre relationship.